- Location
- Level 02 · Corridor B · Grid B-7
- Observed condition
- The duct elevation shown on M-211 conflicts with the ceiling elevation shown on A-402.
- Affected work
- Duct installation and ceiling framing in Corridor B.
- Decision needed
- Confirm the required routing or approved ceiling adjustment before installation.
- Field status
- Work held only in the affected area pending reviewed direction.
See one field issue become a controlled RFI.
This example uses fictionalized project information. It demonstrates the review path without creating an account, uploading a file, or implying that AI can approve project direction.
Capture the condition before work proceeds.
Describe only what is known, connect evidence, and state the decision the field needs.
What the Superintendent provides
- Exact location and observable condition
- Photograph and drawing references
- Trade and sequence affected
- Safe interim action and decision deadline
Human authority: The Superintendent controls the immediate field response; CONHUBAI does not issue direction.
Check completeness before drafting.
The preflight separates usable facts from missing information and unsupported assumptions.
Field description, affected area, and current work status are specific.
A-402 Rev 6 and M-211 Rev 4 are identified for comparison.
Confirm when the affected sequence reaches the hold point.
Do not state an impact until the responsible team verifies it.
Prepare an answerable, source-backed RFI.
The draft preserves missing facts instead of inventing them.
Corridor B duct and ceiling elevation conflict
Condition
M-211 Revision 4 indicates duct routing at an elevation that conflicts with the finished ceiling elevation indicated on A-402 Revision 6 at Corridor B, Grid B-7. The affected installation is held locally pending reviewed direction.
References reviewed
- A-402 · Reflected Ceiling PlanRevision 6 · issued for constructionShows ceiling elevation and diffuser layout.
- M-211 · Level 02 Duct PlanRevision 4 · issued for constructionShows main duct elevation through Corridor B.
- Specification 23 31 00Issued Addendum 03Defines coordination and installation requirements.
- Field photo FP-018Captured 2026-07-28 · sanitizedShows the above-ceiling condition at Grid B-7.
Requested direction
Confirm the required duct routing, approved ceiling adjustment, or other coordinated direction. Identify any revised drawing or detail that governs the installation.
Unresolved information
[Confirm decision date] · [Confirm whether a verified cost or schedule effect exists] · [Attach the approved field markup if created]
Review authority, exposure, and issue readiness.
Connect approved direction to accountable action.
CONHUBAI can organize the handoff, but approved project direction must come from the responsible authority and remain in the project system of record.